Road · Laid out 1911

Doherty Avenue

Doherty Avenue
Location Map
Neighborhood Pinedale Park
Laid Out 1911
Right of Way 40 ft
Pavement 15 ft


Doherty Avenue is a short street in the Pinedale section of Pinehurst, at the Burlington line, running about 580 feet from Boston Road to the foot of Crystal Street. It has had three names. It began as Oak Street on the plan "Pinedale Park Addition, Billerica, Mass.," drawn in April 1911 by C. A. Thayer, engineer, and recorded on December 22, 1911 (Plan Book 29, Plan 3), part of the lots of Pinedale Park. On that plan Oak Street runs across the lower end of the addition, one row of lots in from "Main Street," as Boston Road was labeled, from Bedford Street past Crown Street and Crystal Street to High Street, with rows of narrow numbered lots on both sides. It should not be confused with the much older Oak Street in North Billerica.

The way remained private and almost empty for most of the century. By 1972 the town's highway lists called it Border Court, and it was graded in 1972, 1978 and 1979. At the annual town meeting session of April 24, 1980, town meeting voted, 62 to 49 and against the advice of the Finance Committee, "to accept the laying out of Border Court formerly also known as Oak Street, from the Town line at Boston Road northerly and then easterly to Crystal Street," a way 40 feet wide and about 555 feet long, "and that the name be changed to Border Court." The Street Acceptance Committee pointed out that there was "only one house on this road." Crown Street and the first 340 feet of Crystal Street were accepted the same evening, and Border Court was hot topped with bituminous concrete that year.

By May 1995 the street was called Doherty Avenue: a deed of that month for lots of the 1911 plan is headed "Doherty Avenue," and houses were built on them in 1995 and 1996. No vote or order changing the name from Border Court has been found, and the origin of the name Doherty was not found. Doherty Avenue was repaved under the town's roadway management contracts in fiscal year 2003.



Doherty Avenue
Pinedale Park Addition, 1911 (Plan 29/3)

References

  1. Town report 1980: April 24, 1980, Border Court formerly Oak Street accepted, 555 feet, and named Border Court
  2. Town report 1980: Highway, Border Ct. hot topped with Type I bituminous concrete
  3. Town report 1972: Highway, streets graded incl. Border Court
  4. Town report FY2003: roadway management contracts, Doherty Ave repaved