Rosewood Avenue is a street in River Pines north of the Centre. It runs east from River Street, near the old line of the Middlesex Turnpike, across Hilltop Road to Bridle Road near the Concord River.

It was laid out on the plan "River Pines Shores, Billerica, Mass.," drawn in August 1934 by Alfred Millhouse, civil engineer, of South Boston for E. B. Hamilton, trustee, of the Old South Building in Boston. The plan was approved by the town's Board of Survey and recorded on August 29, 1934 (Plan Book 58, Plan 43). It shows Rosewood Avenue 40 feet wide, running west from Bridle Road across Hilltop Road to the western edge of the tract, which was bounded by land "form. Baldwin, now Mitchell" and marked "Unit 6." To the north were the back lots of Pinewood Avenue in River Pines Unit 5, and to the south was Limewood Avenue. Most of the lots were 50 by 100 feet. Like the other streets on the 1934 plan (Limewood, Edenwood, Robinwood, Balsamwood, Alderwood and Eastwood), it was given a name ending in "wood." No record found explains why Rosewood was chosen. The western part of the street, between the 1934 tract and River Street, appears in town records as Rosewood Avenue Extension from 1972 on. The plan that laid out that part has not been found.

Rosewood Avenue was the first street on the River Pines Shores plan to become a public way. The annual town meeting of February 1950 dismissed an article to accept it. A special town meeting on July 17, 1950 then voted "that Rosewood Avenue be accepted as or for a public highway" (Article 11). Water mains were laid in it the next two years, 1,148 feet in 1951 and 718 feet in 1952. In 1953 the highway department reported it "graveled and asphalt penetrated for 2000 feet." The town hot-topped Rosewood Avenue with bituminous concrete in 1970 and did drainage work on it in 1971 and 1972. It graded the extension in 1972 and hot-topped it in 1975.



Rosewood Avenue
River Pines Shores, 1934 (Plan 58/43)

References

  1. Annual Report 1950: special town meeting of July 17, 1950 votes that Rosewood Avenue be accepted as a public highway (Art. 11)
  2. Annual Report 1950: special town meeting warrant, Art. 11, to accept the laying out of Rosewood Avenue as a town way
  3. Annual Report 1951: water main extended 1,148 feet in Rosewood Avenue
  4. Annual Report 1952: water main extended 718 feet in Rosewood Avenue
  5. Annual Report 1953: Rosewood Avenue graveled and asphalt penetrated for 2,000 feet
  6. Annual Report 1956: list of streets accepted by the town, "Rosewood Ave. 7-17-50"
  7. Annual Report 1970: Rosewood Avenue hot topped with Type I bituminous concrete
  8. Annual Report 1971: drainage project on Rosewood Avenue (partial)
  9. Annual Report 1972: Rosewood Avenue Ext. among streets graded
  10. Annual Report 1972: Rosewood Avenue among drainage projects
  11. Annual Report 1975: Rosewood Avenue Ext. hot topped with Type I bituminous concrete