Road · Laid out 1971

Fardon Street

Fardon Street
Location Map
Neighborhood Green Valley Acres
Laid Out 1971


Fardon Street is a street of Green Valley Acres, north of Nutting's Lake. It runs about 2,770 feet from Glad Valley Drive south past the end of Clermore Road, then bends east along the north edge of the old Nutting's Lake lots to Pond Lane Extension near Friendship Street. It was laid out on the "Definitive Plan, Subdivision Plan of 'Green Valley Acres' in Billerica, Massachusetts," owned by Home Towne Builders, Inc. and drawn by Anthony J. Canon, registered land surveyor and professional engineer, of Marlborough, dated January 1965. The town clerk received notice of the Planning Board's approval on March 31, 1965, and the plan was recorded on June 8, 1965 in eight sheets (Plan Book 102, Plan 10). The plan lined Fardon Street with lots 39 to 46 and 82 to 104 and showed the paper streets of the Nutting's Lake plans, Rhodes, Everett, Fenner, Bunker and Clinton Streets, running up to it from the south. The origin of the name was not found.

Fardon Street was built several years after Glad Valley Drive. The town engineer's report for 1972 speaks of "the continuation of construction of Fardon Street," and the assessors date most of its first houses to 1971 to 1973; a second group was built in 1982 to 1984. In 1973 the town laid an eight-inch water main on Pond Lane "between Friendship Street and the end of Fardon Street," completing a loop along Fardon Street. The highway department graded the street in 1980 and 1981. The Board of Health reported the construction of the "Fardon Street interceptor" sewer in 1978, and the town's ten-mile sewer project of 1989 to 1991 included a pumping station on Fardon Street, the last piece of that project to be finished. On October 13, 1988 the fall town meeting discontinued the short stub of Everett Street between Fardon Street and the Nutting Lake Park Plan C lots, 50 feet wide and 246.68 feet long; Selectman Doyle explained that the Planning Board had already amended the original subdivision plan in 1969 and that the vote was "just to clear up a cloud at the Registry."

The Planning Board submitted Fardon Street for acceptance in 1974, when the town meeting deferred all the streets in the warrant to a new Street Acceptance Committee, and on April 24, 1975 the motion on Fardon Street was dismissed. The street remained private for more than forty years. At the annual fall town meeting of 2018, in its session of October 11, 2018, the town accepted it as a public way under Article 40, "from Glad Valley Drive to Pond Lane Extension, approximate length 2,770' and 50' wide right of way," as shown on a plan of its existing condition drawn on September 20, 2002 by Allen & Major Associates, Inc.; the vote on the article was 137 to 10. Fardon Street was repaved in the fiscal year 2021.



Fardon Street
Green Valley Acres, 1965 (Plan 102/10)

References

  1. 1972 Engineering report: continuation of construction of Fardon Street
  2. 1973: eight-inch water main on Pond Lane between Friendship Street and the end of Fardon Street
  3. 1974 town meeting, Art. 14: acceptance of Fardon Street and other streets deferred to a Street Acceptance Committee
  4. April 24, 1975 town meeting, Art. 14: Fardon Street dismissed
  5. 1978 Board of Health: construction of the Fardon Street interceptor sewer
  6. 1980 Highway Department: Fardon Street among streets graded
  7. Oct. 13, 1988 town meeting, Art. 35: Everett Street stub between Fardon Street and Nutting Lake Park Plan C discontinued
  8. Oct. 13, 1988: Selectman Doyle on the 1969 amendment of the subdivision plan; motion carried
  9. 1989: new sewer pumping station to be installed on Fardon Street
  10. 1990: ten-mile sewer project complete except the Fardon Street pump station
  11. Fall 2018 warrant Art. 40: Fardon Street, Glad Valley Drive to Pond Lane Extension, 2,770 ft, 50 ft wide
  12. Oct. 11, 2018 town meeting, Art. 40: listed roads accepted as public ways, 137 to 10