Road · Laid out 1953

Route 3

Route 3
Location Map
Laid Out 1953
Right of Way 50 - 300 ft
Pavement 20 - 36 ft


Route 3 is the Northwest Expressway, the limited access, divided highway that carries U.S. Route 3 through the west and south of Billerica, about six and a half miles from the Bedford and Burlington lines in the south to the Chelmsford line near Chelmsford Road (Route 129) in the north. It crosses the Concord River in South Billerica and has interchanges at Concord Road and Treble Cove Road; Rangeway Road crosses it on an overpass. Before the expressway, Route 3 between Boston and Lowell ran over the old roads through the town centers, in Billerica over Boston Road and Chelmsford Road. That line became Route 3A, and in 1953 the selectmen were already writing of "the junction of Routes 3 and 3A" at Chelmsford Road.

A bypass of the old road around Chelmsford center had opened in 1941, and in 1949 the Billerica school report expected growth "when a new Lowell Turnpike is constructed through West and South Billerica as now planned." The Massachusetts Department of Public Works laid out the Billerica section as a limited access state highway in two layouts: No. 3937 of February 5, 1952, from the Bedford line, and No. 4072 of September 15, 1953, from the end of that layout to the Chelmsford line. The plan of the second, "Plan of Road in the town of Billerica, Middlesex County, Laid out as a State Highway by the Department of Public Works, September 15, 1953," fills twenty-seven sheets, and the order of taking, recorded on October 2, 1953 (Book 1236, Page 297), described the work as the limited access relocation of the Middlesex Turnpike "to become Route 3." Much of the new road follows the general line of the Middlesex Turnpike of 1806, which had crossed the Concord River about a mile above the center bridge. The state also laid out, on behalf of the town, new pieces of Concord Road, Rangeway Road, Winning Road and Treble Cove Road where they met the highway, and changed the access at Manning Road and Eliot Street in May 1953.

Construction ran from 1952 to 1955. The bridges in Billerica were built in 1953: a pair of reinforced concrete arches over the Concord River, designed by the engineer Hugh P. Duffill, steel overpasses carrying Concord Road, Rangeway Road, Treble Cove Road and Manning Road over the highway, a bridge over a farm road west of the river, and a culvert at Mill Brook. In 1954 the town voted $21,750 "for the purpose of reimbursing the State for the Town's share of expense in construction of roadways and watermains at the overpasses on Concord Road, Rangeway Road and Treble Cove Road." After three years of construction the extension from Chelmsford south to Route 128 in Burlington was opened to traffic in 1955. Where Concord Road had been moved, the town discontinued the old piece of Concord Road "lying between the easterly location line of state highway Route 3" and the Old Middlesex Turnpike by a unanimous vote in 1965.

The highway turned the farmland and woods along it toward industry. From 1955 on, articles to rezone land "on the new Route 3" near Treble Cove Road and Rangeway Road for business and industry came before town meeting; in 1960 seven of the eight rezoning articles of the town's Industrial Commission were voted. In 1955 an article asked the selectmen to petition the state for "a half cloverleaf, to be constructed at the Rangeway Road overpass"; no such interchange was built. The commission put up "Elbow Room" signs on Route 3 in 1960. Minneapolis-Honeywell bought land on the west side of the highway near Concord Road in 1961 and three years later planned a 250,000 square foot building there to employ 2,000 people. In 1964 the commission was urging the extension of Route 3 to the Inner Belt in Boston, which was never built. The state altered the layout at Rangeway Road in 1959 and at Concord Road in 1996, and the county relocated part of Treble Cove Road next to the highway in 1959.

By the 1990s the four-lane road was badly congested. In the Route 3 North project, built under a design-build-operate contract, Modern Continental Construction widened the 21 miles of Route 3 from Route 128 to the New Hampshire line to three lanes in each direction, at a cost of about $385 million. Work began in April 2001, three lanes were open in each direction by October 2004, and the project was finished in 2005. In Billerica the river arches and most of the 1953 bridges were replaced, the river bridge in 2004, and the state made new layouts at Treble Cove Road, Rangeway Road and the old Manning Road in 2002. The Billerica interchanges, once exits 27 (Concord Road) and 28 (Treble Cove Road), are now numbered by mileage as exits 76 and 78.



Route 3
Plan for Route 3, 1953 (Plan 0/344)
Route 3
Treble Cove Road (Route 3 Change), 1959 (Plan 910/38)

References

  1. Annual Report 1949: school report expects growth when a new Lowell Turnpike is built through West and South Billerica
  2. Annual Report 1953: selectmen on water mains at the junctions of town roads with the new Route 3; junction of Routes 3 and 3A
  3. Warrant (1953 report): Art. 38, $21,750 for the town's share at the overpasses on Concord, Rangeway and Treble Cove Roads
  4. Annual Report 1954: accounts, Overpasses, Concord, Rangeway and Treble Cove Roads
  5. Annual Report 1955: warrant Arts. 29-30, rezoning land on the new Route 3 near Treble Cove and Rangeway Roads
  6. Annual Report 1955: warrant Art. 50, petition for a half cloverleaf at the Rangeway Road overpass
  7. Annual Report 1960: Industrial Commission, rezoning along Route 3 and Elbow Room signs on Route 3
  8. Annual Report 1964: Industrial Commission on Minneapolis-Honeywell and the extension of Route 3 to the Inner Belt
  9. Annual Report 1965: Art. 73 voted unanimously, discontinuing old Concord Road east of the Route 3 location line
  10. Massachusetts state highway layouts in Billerica: Route 3 layouts 3937 (1952), 4072 (1953) and later alterations to 2002
  11. Steve Anderson, Northwest Expressway (US 3): 1941 Chelmsford bypass, 1955 opening to Burlington, 2001-2005 widening
  12. FHWA project profile: Route 3 North design-build-operate widening, $385 million, completed 2005
  13. U.S. Route 3 (Wikipedia): Northwest Expressway history and exit list (Concord Road 76, Treble Cove Road 78)


Deed References

Date Type Grantor Grantee Summary Recorded
October 2, 1953 Taking Ozeline Wise et al. Commonwealth of Massachusetts 1236/297
May 26, 1961 Quitclaim Deed Ralph W. Stoker and Claire H. Stoker of Billerica Minneapolis-Honeywell Regulator Company (Delaware corporation) 1514/548
May 26, 1961 Quitclaim William E. Davis and Naomi M. Davis of Billerica Minneapolis-Honeywell Regulator Company, a Delaware corporation of Wellesley 1514/553